Convenience wrapper that fits a control chart and tags its phase as
"phase_1" (the default for any chart constructor). The intent is
to make Phase I usage explicit in code: the practitioner
acknowledges that limits are being estimated.
Arguments
- data
A data frame.
- ...
Arguments passed to a chart constructor.
- chart
A character key naming the chart constructor:
"i_mr"(default),"xbar_r","xbar_s","p","np","c","u","regression","ewma","cusum","hotelling","mewma","mcusum".- trim_outliers
Logical. If
TRUE, iteratively drop observations that violate the rules and re-estimate limits (Montgomery 2019, Section 6.2.3).- max_trim_iter
Integer. Maximum trimming iterations.
Value
A shewhart_chart object with $phase = "phase_1".
Details
Optionally drops violations from the in-control estimate ("trimmed" calibration), per the iterative procedure described in Montgomery (2019) Section 6.2.3: if any observation falls outside the limits, it is removed and the limits are recomputed; iterate until either all remaining points are in control or no further trimming is possible.
References
Woodall, W. H. (2000). Controversies and Contradictions in Statistical Process Control. Journal of Quality Technology, 32(4), 341-350. doi:10.1080/00224065.2000.11980013
Montgomery, D. C. (2019). Introduction to Statistical Quality Control (8th ed.). Wiley. Section 6.2.3.
Examples
set.seed(1)
df <- data.frame(y = c(rnorm(40, mean = 100, sd = 2), 110, rnorm(20, 100, 2)))
calib <- calibrate(df, value = y, chart = "i_mr", trim_outliers = TRUE)
#> ℹ Trim iteration 1: dropping 1 observation.
calib$n # 60 if trim was avoided, fewer if outliers were removed